BT Energy Co., Ltd
company
2020's
2020's
01
02
03
04
For the first MBHT technology test
From Wonju wastewater treatment plant to river
Design for 10kw of waste discharge channel
Work Complete
05
08
For the first MBHT technology test
From Wonju wastewater treatment plant to river
Installation for 10kw of wastewater discharge channel
09
For the first MBHT technology test
From Wonju wastewater treatment plant to river
Started power generation for 10kw in the discarded effluent waterway
USA, Canada, Russia, China, Japan, Australia, UK,
New Zealand, Germany, France, Spain, Austria,
Turkey, Italy, Greece, Hungary, Netherlands,
Denmark, Czech Republic, Belgium, Iceland, Estonia,
Sweden, Cyprus, Ireland, Poland, Finland,
Bulgaria, Romania, Croatia, Slovenia, Luxembourg, Slovakia, Serbia, Latvia, Lithuania, Philippines, Indonesia, India, Vietnam
10
Industry-University Simulation and Academic Data
Start collaboration for 10-30kw
11
Wonju sewage treatment plant installed in 2021
Proposal consultation for 50kw
2021 Promotion Schedule
02
04
Second test of MBHT technology
For 100kw discharge waterway of thermal power plant
Selection of certified and pilot plants
(selected among southeast, west, south, central, and east-west power generation)
Gangwon-do River and Seoul’s Han River, etc.
Selected for 100-500kw for testing with the competent department
(More than 1 each)
05
Jeju Island and South Coast Aquaculture Plant Discharge Pipeline
Consultation on selection of installation company for 10-1,000kw
06
For the second test of MBHT technology
Manufactured for 100kw discharge waterway from thermal power plant
08
For the second test of MBHT technology
Demonstration power generation for 100kw discharge waterway from thermal power plant
10
For the third generation of MBHT technology
For 1,000kw discharge waterway from thermal power plant
Power plant selection consultation
(selected among southeast, west, south, central, and east-west power generation)
11
Completed trial installation for 100kw Uldolmok
12